Flowell Electric Association

Utah Utility Interconnection & net metering rules
Line Taps Allowed0
Load Taps Allowed0

Net metering & export

Rebates Offered
0

Interconnection & taps

Approval Req To Install
Yes
Interconnection Level
3
Line Taps Allowed
0
Load Taps Allowed
0
Automatic Transformer Upgrade Size
0

System size & offset

System Size Restrictions
0
System Size Restriction Type
No Restrictions
System Size Battery Included
0
System Size Includes Existing Systems
0
Offset Type
No Restrictions
Offset Value
0
Offset Calculation Period
0
Industry Standard Watts Sqft
2
Offset Calc Tool
N/A

Metering & disconnect

Production Meter Required
No
Production Meter Position
N/A
Production Meter Labeling
N/A
Allowed Meter Adapter
None

Plans & docs

SLD Reqs
For a 6000 Inverter please use a 40A 2P Breaker. There is a shortage of 35A Breakers - 11.23.20
Install Reqs
Must contact them for Final Inspection - Brandon @
Placards
AC Disconnect:
Must be permanently and visible, marked as “GENERATOR DISCONNECT” in letters at least 2” high
If the AC Disconnect is not adjacent to the electrical service entrance equipment, a permanent/weather resistant map shall be installed at that location detailing where the Isolation Switch is located
Website
link
Phone
(435) 743-6214

Other details

Restrict Inspection
0
Address ID
108116
Express Planset Eligible
Yes
Compiled from public records, 2026. Tariffs and interconnection rules change; verify with Flowell Electric Association before you rely on this. The useful move: if an installer says you need a main panel upgrade, ask how these tap and interconnection policies were considered first.