Hyrum City Electric Department
Net metering & export
- Net Metering Allowed
- 0
- TOU Utility
- 0
- Post Solar Billing Method
- Feed-in-Tariff
- Solar Export Type
- Fixed kWh
- Solar Export Rate
- 0.04
- Net Excess Generation Notes
Purchase all energy produced at $0.04/kWh
- Rebates Offered
- 0
- Deregulated
- 0
Interconnection & taps
- Approval Req To Install
- No
- Interconnection Level
- 3
- Line Taps Allowed
- 0
- Load Taps Allowed
- 0
- Automatic Transformer Upgrade Size
- 0
- Meter Aggregation Allowed
- 0
System size & offset
- System Size Battery Included
- 0
- System Size Includes Existing Systems
- 0
- Offset Value
- 0
- Offset Calculation Period
- 0
- Industry Standard Watts Sqft
- 2
- System Offset Notes
Residential: 10 kW
Commercial: 50 kW
- Offset Calc Tool
- N/A
Metering & disconnect
- Production Meter Required
- Yes
- Production Meter Position
- Inv-Disco-PM-Disco-POI
- AC Disconnect Required
- Yes
- Allowed Meter Adapter
- None
Plans & docs
- Site Plan Reqs
Site plans showing the physical layout of the Generating Facility and the location of associated structures and infrastructures such as buildings, streets, driveways, water ways, fences, the customer generating equipment and the City's associated distribution system equipment.
- SLD Reqs
A single-line and three-line drawing showing the electrical relationship and descriptions of the significant electrical components such as the primary switchgear, secondary switchboard, protective relays, transformers, generator, circuit breakers, with operating voltages, capacities, and protective functions of the Generating Facility, the customers load, and the interconnection with the City's distribution system which is typically the City's transformer
For a 6000 Inverter please use a 40A 2P Breaker. There is a shortage of 35A Breakers - 11.23.20
A dedicated PV system production meter between the inverter and customer-provided AC disconnect switch is required
- Install Reqs
Each GF installation must include a manually operated, lockable, disconnect switch with a visual break. The disconnect switch must be visible and accessible at all times by Hyrum City Electric Department. personnel to allow the GF to ben disconnected safely during maintenance or outage conditions. In the case of a PV system, this disconnect switch must be located next to the Hyrum City Electric Department electric meter. Thedisconnect switch shall be permanently labeled with text indicating that the switch is for the GF. The labeling shall also clearly indicate the open and closed position of the switch. The disconnect switch must be located on the output or load side of the GF such that the entire GF can be isolated from Hyrum City Electric Department distribution system. If the site contains several generators, a single disconnect switch may be used providing its rating is sufficient for all generators and opening it produces a visible open point between all generators and the Hyrum City Electric Department system.
- Meter Num Req SLD 3LD
- 0
- ESID Num Req SLD 3LD
- 0
- Website
- link
- Phone
- (435) 245-6033
Other details
- Restrict Inspection
- 0
- Revision Required
- 0
- Mod Swap Requires Planset
- 0
- Address ID
- 142152
- Express Planset Eligible
- No