Manti City
Net metering & export
- Net Metering Allowed
- 1
- NEM Type
- Monthly
- Post Solar Billing Method
- Net Metering
- Net Excess Generation Notes
Meters are read at then end of each month and the customer is either charged for or credited the difference. If there is a positive difference, a monetary credit will be given which will roll over month-to-month. Accounts are settled in April of each year.
- Rebates Offered
- 0
- Deregulated
- 0
Interconnection & taps
- Approval Req To Install
- Yes
- Interconnection Level
- 3
- Supply Side Taps Allowed
- 0
- Line Taps Allowed
- 0
- Load Taps Allowed
- 0
- Automatic Transformer Upgrade Size
- 0
System size & offset
- System Size Battery Included
- 0
- System Size Includes Existing Systems
- 0
- Offset Value
- 0
- Offset Calculation Period
- 0
- Industry Standard Watts Sqft
- 2
- System Offset Notes
A customer-owned generation facility and net metering system, with a generating capacity of not more than twenty-five kilowatts aggregated at the service interconnection point, in parallel with Manti City's electrical system.
Metering & disconnect
- Allowed Meter Adapter
- None
Plans & docs
- SLD Reqs
Production meter is not required.
Generator (PV Panels, Wind Turbine, Hydro Turbine, etc.) - Include manufacturer, part number, nameplate maximum capacity (kW), and physical location. For modular systems (e.g. pv panels), also include: number of modules, configuration, nameplate maximum capacity of each module, and total nameplate maximum capacity.
Inverter - include manufacturer, type of series, part number, nameplate maximum capacity (kW), output voltage, physical location.
Disconnect Switch - Include the physical location relative to the Manti City Service Meter.
Electrical Service Panel - Include the panel or main breaker size and the position at which the generation is connected. Show all panels (if there are multiple panels or subpanels) even if not directly connected into the generation system.
Manti City Service Meter - Include existing meter serial number, meter form and class.
Other Related Equipment (battery banks, transfer or bypass switches, backup generators, etc.).
- Install Reqs
Production meter is not required.
Customer shall furnish and install on customer's side of the meter, a UL-approved safety disconnect switch which shall be capable of fully disconnecting the Customer's generating facility from Manti City's electric system. The disconnect switch shall be located adjacent to Manti City's meters and shall be of the visible break type in a metal enclosure which can be secured by a padlock. The disconnect switch shall be accessible to Manti City personnel at all times.
- Placards
Meter and transformer of transformer pole serving the Customer Generator shall be labeled to indicate potential electric current feedback. Manti City will provide and install labels when Customer-Generator's electrical system is approved for interconnection.
- Equipment Approvals
- California Energy Commission
- Label Page Notes
Reference Utah Labels block
- Website
- link
- Phone
- (435) 835-2401
Other details
- Restrict Inspection
- 0
- Address ID
- 651542
- Express Planset Eligible
- Yes