City of Ellensburg

Washington Utility Interconnection & net metering rules
Net Metering Allowed1
NEM TypeAnnual
Line Taps Allowed0
Load Taps Allowed0
AC Disconnect RequiredYes

Net metering & export

Net Metering Allowed
1
NEM Type
Annual
TOU Utility
0
Post Solar Billing Method
Net Metering
Net Excess Generation Notes

Net Metering of electricity measures electricity flowing both directions at a location with solar panels. The customer still pays the appropriate customer charge for the billing period. Generation up to consumption for the billing period is credited at the retail rate (same rate as charged). For example, if generation is greater than the locations energy consumption only the customer charge will be billed. If consumption is greater than generation the 'net difference' will be billed. Excess energy produced by the solar system will be 'banked' by the utility for use in a future billing period. On April 30th of each calendar year, any remaining unused kilowatt-hour credit accumulated during the previous year shall be purchased by the electric utility at the average wholesale cost of power.

Rebates Offered
0
Allows Standby
0

Interconnection & taps

Approval Req To Install
Yes
Interconnection Level
3
Line Taps Allowed
0
Load Taps Allowed
0
Automatic Transformer Upgrade Size
0
Meter Aggregation Allowed
1

System size & offset

System Size Restrictions
0
System Size Restriction Type
No Restrictions
System Size Battery Included
0
System Size Includes Existing Systems
0
Offset Type
Percentage
Offset Value
100
Offset Calculation Basis
Historical
Offset Calculation Period
12
Industry Standard Watts Sqft
2

Metering & disconnect

Production Meter Required
No
AC Disconnect Required
Yes
AC Disconnect Labeling
Visible Lockable Labeled Disconnect

Plans & docs

Equipment Approvals
California Energy Commission
Meter Num Req SLD 3LD
0
ESID Num Req SLD 3LD
0
Website
link
Phone
(509) 962-7124

Other details

Restrict Inspection
1
Revision Required
1
Mod Swap Requires Planset
1
Address ID
4470661
Express Planset Eligible
Yes
Compiled from public records, 2026. Tariffs and interconnection rules change; verify with City of Ellensburg before you rely on this. The useful move: if an installer says you need a main panel upgrade, ask how these tap and interconnection policies were considered first.