Net Metering AllowedYes
NEM TypeAnnual
Line Taps AllowedNo
Load Taps AllowedNo
AC Disconnect RequiredYes

Net metering & export

Net Metering Allowed
Yes
NEM Type
Annual
TOU Utility
No
Post Solar Billing Method
Net Metering
Solar Export Type
N/A
Net Excess Generation Notes

If the electricity generated by the Member and distributed back to Tanner during the billing period, exceeds the electricity supplied by Tanner, then the Member shall be: (a) billed for the appropriate Member service charge as other Members of Tanner in the same rate class; and (b). credited for the net excess kilowatt-hours generated during the billing period, with this kilowatt-hour credit appearing on Member’s bill. Beginning April 1 of each year, any remaining unused kilowatt-hour credit accumulated by the Member during the previous 12 months shall be granted to Tanner, without any compensation to the Member.

Rebates Offered
No
Deregulated
No
Allows Standby
No

Interconnection & taps

Approval Req To Install
Yes
Line Taps Allowed
No
Load Taps Allowed
No
Automatic Transformer Upgrade Size
0
Meter Aggregation Allowed
No

System size & offset

System Size Restrictions
100
System Size Restriction Type
AC kW
System Size Battery Included
No
System Size Includes Existing Systems
No
Offset Value
0
Offset Calculation Period
0
Industry Standard Watts Sqft
2
System Offset Notes

Up to 100 kW AC - transformer upgrade will be customer's responsibility

Offset Calc Tool
Historical Usage

Metering & disconnect

Production Meter Required
No
Production Meter Position
N/A
Production Meter Labeling
N/A
AC Disconnect Required
Yes
AC Disconnect Labeling
Utility Disconnect Switch

Plans & docs

Equipment Approvals
California Energy Commission
Meter Num Req SLD 3LD
No
ESID Num Req SLD 3LD
No
Rate Schedule Link
link
Website
link
Phone
(425) 888-0623

Other details

Revision Required
Yes
Mod Swap Requires Planset
Yes