New Richmond Utilities

Wisconsin Utility Interconnection & net metering rules

Spot something wrong?

Tariffs and interconnection rules move often. If something here is out of date or missing, tell us and we'll fix it.

Report a correction
Net Metering AllowedYes
NEM TypeMonthly
Line Taps AllowedNo
Load Taps AllowedNo
AC Disconnect RequiredYes

Net metering & export

Net Metering Allowed
Yes
NEM Type
Monthly
TOU Utility
No
Post Solar Billing Method
Net Metering
Net Excess Generation Notes

For systems 20 kW or less, any energy exported to the grid will be credited at the full retail rate. At the end of each billing cycle, if there is a remaining credit balance, it will over indefinitely until it is fully used. If the credit balance exceeds $25, the customer has the option to request a payout.

Rebates Offered
Yes
Deregulated
No
Allows Standby
No

Interconnection & taps

Approval Req To Install
Yes
Line Taps Allowed
No
Load Taps Allowed
No
Automatic Transformer Upgrade Size
0
Meter Aggregation Allowed
No

System size & offset

System Size Restrictions
20
System Size Restriction Type
AC kW
System Size Battery Included
No
System Size Includes Existing Systems
No
Offset Type
No Restrictions
Offset Value
0
Offset Calculation Period
0
Industry Standard Watts Sqft
2
Inverter Oversize Restrictions
No

Metering & disconnect

Production Meter Required
No
Production Meter Position
N/A
Production Meter Labeling
N/A
AC Disconnect Required
Yes
AC Disconnect Labeling
Visible Lockable Labeled Disconnect
Allowed Meter Adapter
None

Plans & docs

Site Plan Reqs

- Street address of DG facility

- Adjoining street name

- Electric service entrance

- Electric meter

- Interface equipment

- Location of major equipment

- Location of interconnect disconnect switch

SLD Reqs

- Generator or inverter

- Point where DG facility is electrically connected to the customer’s electrical system

- Point of common coupling

- Lockable interconnection disconnect switch (outside)

- Method of grounding, including generator and transformer ground connections

- Protection function and systems

Equipment Approvals
California Energy Commission
Meter Num Req SLD 3LD
No
ESID Num Req SLD 3LD
No
Rate Schedule Link
link
Website
link
Phone
(715) 246-4167

Other details

Revision Required
Yes
Mod Swap Requires Planset
Yes
Compiled from public records, 2026. Tariffs and interconnection rules change; verify with New Richmond Utilities before you rely on this. The useful move: if an installer says you need a main panel upgrade, ask how these tap and interconnection policies were considered first.