Oconomowoc Utilities
Net metering & export
- Net Metering Allowed
- 1
- NEM Type
- Monthly
- TOU Utility
- 0
- Post Solar Billing Method
- Net Metering
- Solar Export Type
- Fixed kWh
- Solar Export Rate
- 0.11
- Solar Export Value Notes
- $11 fixed monthly charge
- Net Excess Generation Notes
If, in any month, the customer’s bill has a credit balance of $25 or less, the amount shall be credited to subsequent bills until a debit balance is reestablished. If the credit balance is more than $25, the utility shall reimburse the customer by check upon request. Monthly credits shall be computed by taking the net excess kilowatt-hours produced times the sum of the applicable energy charge plus monthly power cost adjustment clause (PCAC).
- Rebates Offered
- 1
- Deregulated
- 0
Interconnection & taps
- Approval Req To Install
- Yes
- Interconnection Level
- 3
- Line Taps Allowed
- 0
- Load Taps Allowed
- 0
- Automatic Transformer Upgrade Size
- 0
- Meter Aggregation Allowed
- 0
System size & offset
- System Size Restrictions
- 0
- System Size Restriction Type
- No Restrictions
- System Size Battery Included
- 0
- System Size Includes Existing Systems
- 0
- Offset Type
- No Restrictions
- Offset Value
- 0
- Offset Calculation Period
- 0
- Industry Standard Watts Sqft
- 2
- System Offset Notes
Oconomowoc Utilities doesn’t have any size restrictions on the size of distributed generation however the purchase of excess generation (energy not used by the owner/customer that is put back into the local distribution network) by Oconomowoc Utilities is determined by the size of the DG installation.
Excess generation by DG installations less than 20 kW in size is purchased according to the Pgs-1 tariff (attached.)
Excess generation by DG installations greater than 20 kW in size is purchased according to the Pgs-2 tariff (attached.)
- Offset Calc Tool
- Historical Usage
Metering & disconnect
- Production Meter Required
- No
- Production Meter Position
- N/A
- Production Meter Labeling
- N/A
- Meter Spot Process
Any PV installation directly or indirectly connected to the utility distribution network has the potential to send power back on to the grid. The utility is required by the Wisconsin Public Service Commission to purchase any excess generation and so all connected distributed generation is required to be metered according to the WI PSC
There is not a separate PV production meter. A bi-directional meter will be installed by the utility.
Installing a bi-directional meter for grid-connected DG applications is a standard practice.
- Allowed Meter Adapter
- None
Plans & docs
- Site Plan Reqs
Site Plan showing major equipment, electric service entrance, electric meter(s), location of distributed generation and interface equipment, protection equipment, location of disconnect switch, adjoining street name, and street address of the distributed generation system.
• System capacity must be 0.5 kWDC or greater.
• System must be installed within 90 degrees of due south. (Azimuth)
• Must be installed with a panel tilt between 10-50 degrees.
• Must have less than 10 percent obstacle shading based on analysis of an industry-accepted tool.
- SLD Reqs
No line-side taps in the homeowner's MSP
No load-side of the utility meter enclosure in the utility meter base
- Install Reqs
An outside AC disconnect that is always accessible to the utility 24/7/365 is required as a safety precaution.
- Rate Schedule Link
- link
- Website
- link
- Phone
- (262) 569-2196
Other details
- Restrict Inspection
- 0
- Address ID
- 167905
- Express Planset Eligible
- Yes