Net Metering AllowedYes
NEM TypeAnnual
Line Taps AllowedNo
Load Taps AllowedNo
AC Disconnect RequiredYes

Net metering & export

Net Metering Allowed
Yes
NEM Type
Annual
TOU Utility
No
Post Solar Billing Method
Net Metering
Net Excess Generation Notes

Monthly credits shall be computed by taking the net excess kWhs produced times the sum of applicable energy charges plus the monthly power cost adjustment charge. If the customer's bill contains a credit of $25 or more the customers can be reimbursed by check upon request. Consumption and production are not metered separately

Rebates Offered
Yes
Deregulated
No

Interconnection & taps

Approval Req To Install
Yes
Line Taps Allowed
No
Load Taps Allowed
No
Automatic Transformer Upgrade Size
0

System size & offset

System Size Restrictions
20
System Size Restriction Type
AC kW
System Size Battery Included
No
System Size Includes Existing Systems
No
Offset Type
Combination
Offset Value
100
Offset Calculation Basis
Historical
Offset Calculation Period
12
Industry Standard Watts Sqft
2
Offset Calc Tool
Historical Usage

Metering & disconnect

Production Meter Required
No
AC Disconnect Required
Yes
AC Disconnect Labeling
Visible Lockable Labeled Disconnect
Allowed Meter Adapter
None

Plans & docs

Site Plan Reqs

Standard

SLD Reqs

Standard

Electric Service Reqs

AC Disconnect Required

  • Switch shall be grounded
  • Must be readily accessible at all times to utility staff
Electrical Stamp Required
No
Equipment Approvals
California Energy Commission
Meter Num Req SLD 3LD
No
ESID Num Req SLD 3LD
No
Website
link
Phone
(608) 482-4736